What do I need to do after receiving the skin pack machine

28-10-2020
  1. The vacuum skin packing machine should be installed in a clean and ventilated workshop. If the vacuum skin packing machine is delivered by logistics, the fixing screws of the parts of the vacuum skin packing machine may be loose due to bumpy transportation, and some parts may even be shaken off. You need to tighten all screws again to remove the parts. Put it back.

  2. Pay attention to the voltage requirements of the body-packing machine, and do not connect the wrong voltage. And pay attention to the power of the skin-packing machine, pay attention to whether the wires are thick enough, and can carry the current required by the skin-packing machine. Otherwise, there will be hidden safety hazards of wire burnout.Under normal circumstances, we will confirm the voltage in advance.

    If the voltage on site is not 3-phase, 380V, 50HZ, we will provide a transformer.

  3. Pay attention to whether the motor of the body-packing machine has forward and reverse rotation. Whether the phase sequence protection device is installed. If this device is not      installed, pay attention to the wiring of the three-phase wire to ensure that the motor rotates forward.

  4. The vacuum system of this machine is a very critical part. Pay attention to clean the vacuum chamber and keep it clean. Don't let iron debris and other debris enter the vacuum system. Add vacuum pump oil regularly, otherwise the life of the vacuum pump will be greatly shortened.

  5. Lubricating oil should be regularly added to the transmission part of the body-packing machine.

      


  